Excel serial date to Day, Month, Year and vise versa

By , 12 Aug 2002
 

Introduction

For a little project of mine, I needed to convert a serial date number to day/month/year (DMY) and vise versa. The serial number came from date field in a converted Paradox database and seemed to be exactly the same as the serial date in Microsoft Excel, hence the article name. After some googling I learned that the Excel serial date is related to Julian date, and found a speedy algorithm to convert these numbers to DMY and vise versa.

Excel Serial Date Number

Now what is an Excel serial date number? 37477 is a serial date number and is the number of days since 1-1-1900. 37477 actually translates to Aug 9, 2002, the date of writing this article.

The number of days since 1-1-1900 isn't that hard to calculate of course, once you know the leap years. Microsoft Excel however contains a bug with its date calculation: it considers 29-02-1900 as a valid date, but 1900 isn't a leap year! 29-02-1900 is not a valid date!

According to the stories, Microsoft decided to duplicate this date bug from Lotus 123, which was the dominating spreadsheet application at the time Excel was being written. This allowed Excel to open Lotus 123 spreadsheets without date problems.

(Note that a serial date number may also contain a fraction that denotes the time. It's actually the percentage of 24 hours, but that's not for this article.)

Mac Excel Serial Date number

Excel on the Apple Mac uses a slightly different Serial Date number base: the number of days since 1-1-1904. That's why Excel also features a "1904 Date System" checkbox in its Options (Calculation tab). I won't go into this futher.

Translating Serial Date Number to DMY

First of all, credit where credit is due. I got the basic algorithm from http://serendipity.magnet.ch/hermetic/cal_stud/jdn.htm. It's about converting a Julian date to DMY using integer calculations. I won't bore you with the theory (following the above hyperlink), but the original Julian has a different base date.

With an addition of a certain number, the algorithm comes close to the Excel serial date. And when the 29-02-1900 issue is handled, we've got an Excel serial date to Day, Month, Year calculation!

void ExcelSerialDateToDMY(int nSerialDate, int &nDay, 
                          int &nMonth, int &nYear)
{
    // Excel/Lotus 123 have a bug with 29-02-1900. 1900 is not a
    // leap year, but Excel/Lotus 123 think it is...
    if (nSerialDate == 60)
    {
        nDay    = 29;
        nMonth    = 2;
        nYear    = 1900;

        return;
    }
    else if (nSerialDate < 60)
    {
        // Because of the 29-02-1900 bug, any serial date 
        // under 60 is one off... Compensate.
        nSerialDate++;
    }

    // Modified Julian to DMY calculation with an addition of 2415019
    int l = nSerialDate + 68569 + 2415019;
    int n = int(( 4 * l ) / 146097);
            l = l - int(( 146097 * n + 3 ) / 4);
    int i = int(( 4000 * ( l + 1 ) ) / 1461001);
        l = l - int(( 1461 * i ) / 4) + 31;
    int j = int(( 80 * l ) / 2447);
     nDay = l - int(( 2447 * j ) / 80);
        l = int(j / 11);
        nMonth = j + 2 - ( 12 * l );
    nYear = 100 * ( n - 49 ) + i + l;
}

DMY to Excel Serial Date

Calculate an Excel serial date from Day, Month, Year. The function assumes that the day, month and year are valid date numbers.

int DMYToExcelSerialDate(int nDay, int nMonth, int nYear)
{
    // Excel/Lotus 123 have a bug with 29-02-1900. 1900 is not a
    // leap year, but Excel/Lotus 123 think it is...
    if (nDay == 29 && nMonth == 02 && nYear==1900)
        return 60;

    // DMY to Modified Julian calculatie with an extra substraction of 2415019.
    long nSerialDate = 
            int(( 1461 * ( nYear + 4800 + int(( nMonth - 14 ) / 12) ) ) / 4) +
            int(( 367 * ( nMonth - 2 - 12 * ( ( nMonth - 14 ) / 12 ) ) ) / 12) -
            int(( 3 * ( int(( nYear + 4900 + int(( nMonth - 14 ) / 12) ) / 100) ) ) / 4) +
            nDay - 2415019 - 32075;

    if (nSerialDate < 60)
    {
        // Because of the 29-02-1900 bug, any serial date 
        // under 60 is one off... Compensate.
        nSerialDate--;
    }

    return (int)nSerialDate;
}

License

This article, along with any associated source code and files, is licensed under The Common Development and Distribution License (CDDL)

About the Author

Victor Vogelpoel
Software Developer (Senior)
Netherlands Netherlands
Member
Victor is consulting in The Netherlands.

His interests include Windows and web application development using .NET technologies and even some Apache/PHP/MySQL...

Sign Up to vote   Poor Excellent
Add a reason or comment to your vote: x
Votes of 3 or less require a comment

Comments and Discussions

 
You must Sign In to use this message board.
Search this forum  
    Spacing  Noise  Layout  Per page   
Questionseriel no to DMYmemberrbsshetty2 Dec '12 - 1:39 
i have one questin i have entered a 40406 in textbox how do i convert it to aug 16 2010
QuestionAlternativememberJamesHoward97224 Jan '12 - 22:33 
How about this alternative:
public static double GetDateTimeAsDouble(DateTime value, bool use1904DateSystem)
{
    return (value - (use1904DateSystem ? new DateTime(1904, 1, 1) : new DateTime(1899, 12, 30))).TotalDays;
}
 
Inverting method can be easily implemented with DateTime.AddDays method.
 
Or you can use this Excel C# / VB.NET library that automatically converts System.Double dates to DateTime.
SuggestionDifferent AlgmemberMemonic15 Dec '11 - 7:02 
Hi, i had to implement the same function in my app, i've tried to use ur alg in FLEX (AS3) but with no sucess, so i builted my own.
 
function DMYtoSerialDate(nDay:int, nMonth:int, nYear:int):int
{
var arrMonthsDays:Array = new Array(31, 28, 31, 30, 31, 30, 31, 31, 30, 31, 30, 31);
var nSerialDate:int= 1;
var mCounter:int = 0;
for(var i:int = 1901; i <= nYear; i++)
{
    if(i%4==0)
        nSerialDate+=366;
    else
        nSerialDate+=365;
}
while(mCounter < nMonth-1)
{
    nSerialDate += arrMonthsDays[mCounter];
    mCounter++;
}
nSerialDate+=parseInt(nDay);
return nSerialDate;
}

GeneralRe: Different AlgmemberVictor Vogelpoel15 Dec '11 - 9:01 
Expensive algorithm and flawed for the leap years...
VictorV

GeneralThanks.membersriest10 Jul '09 - 10:01 
Thank you so much for the code.It helped me a lot.
GeneralHi. Thanks for the invaluable contribution. I have found a bug....memberMember 402179718 Nov '08 - 6:57 
I have run a dummy test. Celled function to convert serial to year, month, day then called straight the other function to convert back those to serial. 1900/02/28 Caused a problem as the output/input was not the same.
Instead of
 
if (nSerialDate < 60) {
    nSerialDate--;
}
 
One needs to write:
 
if (nSerialDate <= 60) {
    nSerialDate--;
}
Here is the complete test code:
 
// date_test.cpp : Defines the entry point for the console application.
//

#include "stdafx.h"
#include <iostream>
 
void ExcelSerialDateToDMY(int nSerialDate, int &nDay, 
						  int &nMonth, int &nYear)
{
	// Excel/Lotus 123 have a bug with 29-02-1900. 1900 is not a

	// leap year, but Excel/Lotus 123 think it is...

	if (nSerialDate == 60)
	{
		nDay    = 29;
		nMonth    = 2;
		nYear    = 1900;
 
		return;
	}
	else if (nSerialDate < 60)
	{
		// Because of the 29-02-1900 bug, any serial date 

		// under 60 is one off... Compensate.

		nSerialDate++;
	}
 
	// Modified Julian to DMY calculation with an addition of 2415019

	int l = nSerialDate + 68569 + 2415019;
	int n = int(( 4 * l ) / 146097);
	l = l - int(( 146097 * n + 3 ) / 4);
	int i = int(( 4000 * ( l + 1 ) ) / 1461001);
	l = l - int(( 1461 * i ) / 4) + 31;
	int j = int(( 80 * l ) / 2447);
	nDay = l - int(( 2447 * j ) / 80);
	l = int(j / 11);
	nMonth = j + 2 - ( 12 * l );
	nYear = 100 * ( n - 49 ) + i + l;
 
//	if (nMonth > 2) nYear -= 1;
}
 
int DMYToExcelSerialDate(int nDay, int nMonth, int nYear)
{
	// Excel/Lotus 123 have a bug with 29-02-1900. 1900 is not a
	// leap year, but Excel/Lotus 123 think it is...

	if (nDay == 29 && nMonth == 02 && nYear==1900)
		return 60;
 
	// DMY to Modified Julian calculate with an extra substraction of 2415019.

	long nSerialDate = 
		int(( 1461 * ( nYear + 4800 + int(( nMonth - 14 ) / 12) ) ) / 4) +
		int(( 367 * ( nMonth - 2 - 12 * ( ( nMonth - 14 ) / 12 ) ) ) / 12) -
		int(( 3 * ( int(( nYear + 4900 + int(( nMonth - 14 ) / 12) ) / 100) ) ) / 4) +
		nDay - 2415019 - 32075;
 
	if (nSerialDate < 60)
	{
		nSerialDate--;
	}
 
	return (int)nSerialDate;
}
 

int _tmain(int argc, _TCHAR* argv[])
{
	
	for (int i=0; i<500001; ++i) {
		int nDay = 0; int nMonth = 0; int nYear =  0;
		ExcelSerialDateToDMY(i, nDay, nMonth, nYear);
		int nSerial = DMYToExcelSerialDate(nDay, nMonth, nYear);
		
		//std::cout << "OK :::" << "nSerial->" << nSerial << " Year->" << nYear << " nMonth->" << nMonth << " nDay->" << nDay << std::endl;
		if (i != nSerial) {
			std::cout << "ERROR ::: " << "nSerial->" << nSerial << " Year->" << nYear << " nMonth->" << nMonth << " nDay->" << nDay << std::endl;
		}
	}
 
	
	return 0;
}
</iostream>

QuestionError in Excel Serial Date to DMY ??memberHarry Adams17 Sep '08 - 17:33 
Hi Victor
 
Thank you for providing this code. It has proved a great time saver... I did
not want to have to work this out from scratch. That said, after working with
your algorithm, I have to say (at risk of great personal embarrassment) that
I am pretty sure there is an error.
 
I cut and pasted your code and then translated it to Fortran. (OK, I'm a dinosaur
but there's lots of Jurassic era F77 code out here). I found that I was getting an
incorrect year value for dates between 1 Mar and end of Dec. At first I thought
it was because of bad arithmetic, but I tried it both with floating point and
with integer codes, and with various amounts of truncating using INT() and NINT(),
but the results were the same. Then I tried coding the entire algorithm in Excel,
and I still obtained the same results. Eventually after poking around a bit more
using a code debugger and looking at the Excel results, I determined that the
problem occurs in the calculation of the i variable. I was able to fix it, both
in F77 and Excel. I will provide the Fortran here (because it might be useful to
another dinosaur hacker). You will see I have inserted an "IF" statement at the
end, which says if the calculated month value is greater than 2 (i.e. March
onwards), then subtract one from the year.
 
To my surprise this seems completely robust. I have tested it for every year from
1901 to 2125 (in an Excel spreadsheet) and it produces dates that agree 100%
with the date value created internally by Excel. If you are interested I can send
you the spreadsheet.
 
Hal.
 
*---------------------------------------------------------------------------------
 
         subroutine ExcelDateToDMY(LDate, Y, M, D)
        
* Translated from 'C' source at http://www.codeproject.com/KB/datetime/exceldmy.aspx?print=true        
 
* Excel/Lotus 123 have a bug with 29-02-1900. 1900 is not a
* leap year, but Excel/Lotus 123 think it is...
 

         implicit none
        
         real*8 LDate
        
         integer*4 Y, M, D
        
         integer*4 idate,
      >               i, j, l, n
        
         idate = NINT(LDate)   ! Compute integer date
        
         if (idate .EQ. 60) then
               Y = 1900
               M = 2
               D = 29
               return
                             
         else if (idate .LT. 60) then
 
* Because of the 29-02-1900 bug, any serial date
* under 60 is one off... Compensate.
 
            idate = idate + 1
  
         end if
 
* Modified Julian to DMY calculation with an addition of 2415019
 
         l = idate + 68569 + 2415019
         n = INT (( 4 * l) / 146097 )
         l = l - INT(( 146097 * n + 3) / 4)
         i = INT((4000 * ( l + 1 )) / 1461001)
         l = l - INT(( 1461 * i ) / 4) + 31
         j = INT(( 80 * l ) / 2447)
        
         D = l - INT (( 2447 * j ) / 80)
        
         l = INT(j / 11)
        
         M = 2 + j - ( 12 * l )
 
         Y = 100 * ( n - 49 ) + i + 1
 
* HA 2008/09/16: Bug fix to original code
         if   (M .GT. 2) Y = Y - 1   ! Reduce Year by 1 if Month >= 3
 
         return
        
         end
GeneralPorted to PHP and fixedmemberLubosdz9 Aug '07 - 0:19 
Yes, it is true, second function returns wrong results. I reckon, that formula is not quite correct.
 
Here are 2 fixed PHP functions for conversion date to EXCEL serialDATE and vice versa.
Both functions have been well tested for dates between 01/01/1900 - 31/12/2099.
 

// Excel/Lotus 123 have a bug with 29-02-1900.
// 1900 is not a leap year, but Excel/Lotus 123 think it is...
function excel_D2DMY($days) {
   if ($days <1) return "";
   if ($days == 60)   {
      return array('day'=>29,'month'=>2,'year'=>1900);
   } else {
      if ($days < 60)   {
         // Because of the 29-02-1900 bug, any serial date
         // under 60 is one off... Compensate.
         ++$days;
      }
      // Modified Julian to DMY calculation with an addition of 2415019
     $l = $days + 68569 + 2415019;
     $n = floor(( 4 * $l ) / 146097);
     $l = $l - floor(( 146097 * $n + 3 ) / 4);
     $i = floor(( 4000 * ( $l + 1 ) ) / 1461001);
     $l = $l - floor(( 1461 * $i ) / 4) + 31;
     $j = floor(( 80 * $l ) / 2447);
     $nDay = $l - floor(( 2447 * $j ) / 80);
     $l = floor($j / 11);
     $nMonth = $j + 2 - ( 12 * $l );
     $nYear = 100 * ( $n - 49 ) + $i + $l;
     $ret = array('day'=>$nDay,'month'=>$nMonth,'year'=>$nYear);
     return $ret;
   }
}
 
/**
* @desc Returns Excel serialDate constant calculated from gregorian date
* original javascript found @ http://wwwmacho.mcmaster.ca/JAVA/JD.html
* ported to PHP by XLSmile | :)
*
* tested compatibility with EXCEL dates between 01/01/1900..31.12.2099,
* year given eventually as 0 (=1900)..199 (=2099)
* adds also days if supplied argument more than real number of days
* in particular month (same applies to months)
* as for years bellow 1900: algorhytm is not exact, therefore limitation
* for years 1900 - 2099
*/
function excel_DMY2D($d, $m, $y, $uh=0, $um=0, $us=0) {
     if($y<1900){
          if($y<0 || $y>199){
               echo ' !!! Invalid year ['.$y.'], must be between 1900 - 2099 or 0 - 199 !!!';
               return false;
          }else{
               $y += 1900;
          }
     }
     $extra = 100.0*$y + $m - 190002.5;
     $rjd = 367.0*$y;
     $rjd -= floor(7.0*($y+floor(($m+9.0)/12.0))/4.0);
     $rjd += floor(275.0*$m/9.0);
     $rjd += $d;
     $rjd += ($uh + ($um + $us/60.0)/60.)/24.0;
     $rjd += 1721013.5;
     $rjd -= 0.5*$extra/abs($extra);
     $rjd += 0.5;
    
     $rjd -= 2415020.5; // JD correction constant for 01/01/1900
     $rjd += ($rjd>60) ? 2 : 1; // adjust to inheritet EXCEL/LOTUS bug
      return $rjd;
}
 
XLubosSmile | :)
QuestionWorks great for date, what about for time?memberTariAbay29 Jul '07 - 20:19 
Thanks for you script, it works great, but i need to also convert time as well.
how can I do that?
 
Tariku Giovanni
Web Consultant

AnswerRe: Works great for date, what about for time?memberMember 22281364 Aug '10 - 16:26 
the same problem
if you konw the solution, please tell me! thank you.
I like c++

General General    News News    Suggestion Suggestion    Question Question    Bug Bug    Answer Answer    Joke Joke    Rant Rant    Admin Admin   

Permalink | Advertise | Privacy | Mobile
Web01 | 2.6.130523.1 | Last Updated 13 Aug 2002
Article Copyright 2002 by Victor Vogelpoel
Everything else Copyright © CodeProject, 1999-2013
Terms of Use
Layout: fixed | fluid